DIYdeals - Assembly Instructions for Raised Decks
5.5m 18'0" wide
 
deck welcomeRaised DecksPergola Decksground decks with 4" planed joistsground decks with 6" planed joists Balustrade
Prices 
Check the size of deck you are building from the list below and if necessary cut the joists 'C, D or E' to the correct length. Then please follow the instructions which are listed beneath the sizes. Some decks have a deck board overhang of the front and back joists - it is best if you lay out the deck boards first over the joists to see if an overhang is required. 
NB the deck boards are designed to be used with the fine ribbed as the surface as it offers a better slip resistance, but you can use it the grooved side if preferred.

E-mail any questions to diydeals@hotmail.co.uk or call 01457 855259

   A

 

 

 

A = recess of side joists, B & F= Gap between support joists, P = total posts

   C

 F

B

  B

 B    B

  B

  B1

   F1  A

G1,2,3 = Post from front & back joists, O/H is the approx. deck board overhang of the front and back joists
      4m Front, Centre & Back Joists      1.5m Front,Centre & Back Joists      Support Joist CDE
       Extra joists to support alternating 1.5m deckboards      Noggins       Posts
 
 

G1

S    

  A=Approx. 4cm 1.5" B=59cm 23"B1= 62cm  F =40cm 16" F1 = 50cm 20" all approx.  

                           T

  size 5.5m wide x

C =

    P= G1

 

 

O/H

  0.6m S 0.45m     8 7cm 3"     3cm 1"

   C

0.9m S 0.75m     8 7cm 3"     3cm 1"
  1.2m S 1.0m     8 7cm 3"     3cm 1"
  1.5m S 1.35m     8 10cm 4"     3cm 1"
  1.8m S 1.65m     8 10cm 4"     3cm 1"
  2.1m S 2.0m     8 20cm 8"     0
  2.4m S 2.25m     8 30cm 12"     3cm 1"
    2.7m S 2.5m     8 30cm 12"     5cm 2"
         U   3.2m S 3.0m     8 30cm 12" centre post noggins 5cm 2"

   C

3.6m S 3.35m     8 50cm 20" centre post noggins 3cm 1"
  size 5.5m wide x

C =

    P= G1     O/H
  3.9m T 3.75m     12 30cm 12"

}

3cm 1"

   D

4.2m T 4.0m     12 30cm 12"

}all with 4" planed

5cm 2"
  4.5mT 4.35m     12 30cm 12"

}centre noggins

3cm 1"
  4.8m T 4.65m     12 40cm 16"

}

  3cm 1"
  5.1m T 5.0m     12 40cm 16"

}

  0
         V   size 5.5m wide x

C =

D =

E =

P= G1 G2   O/H
5.7m U 3.0m 2.5m 8+8 30cm 12" 30cm 12" 5cm 2"

   C

6.3m U 3.0m 3.0m   8+8 30cm 12" 30cm 12"   5cm 2"
  6.6m V 4.0m 2.4m   12+8 30cm 12" 30cm 12"   3cm 1"
  7.2m V 4.0m 3.0m   12+8 30cm 12" 30cm 12"   5cm 2"

   D

7.7m V 5.0m 2.5m   12+8 40cm 16" 30cm 12"   3cm 1"
8.3m V 5.0m 3.0m   12+8 40cm 16" 30cm 12"   5cm 2"
  9.3m 5.0m 4.0m   12+12 40cm 16" 30cm 12"   5cm 2"
  10.2m 5.0m 5.0m   12+12 40cm 16" 40cm 16"   3cm 1"

   C                    W

 

size 5.5m wide x

C =

D =

E =

P=

G1 G2 G3

O/H

11.3m W 3.0m 5.0m 3.0m 8+12+8 30cm 12" 40cm 16" 30cm 12" 5cm 2"
  12.3m Y 4.0m 4.0m 4.0m 8+12+8 Y 30cm 12" Y 5cm 2"

 

13.2m Y 4.0m 5.0m 4.0m 8+12+8 Y 30cm 12" Y 0

   D

14.3m Z 5.0m 4.0m 5.0m 12+8+12 30cm 12" 1m 34" Z 30cm 12" 5cm 2"
  15.3m X 5.0m 5.0m 5.0m 12+12+12 40cm 16" 40cm 16" 40cm 16" 5cm 2"

   E

Y has 1 post 30cm from end and the other with an approx.1.6m from the middle deck so that the  posts are not more than 2.25m apart (from front to back) see below
                   

                           X

 

  Y 

              Z      

   C

                 
 
                 

   D

                 
                   
                   

  

                 

   E

                 
                   

 

1.  For Raised Patio Decks 5.5m wide

Before starting erection of Deck

Please note that deck-boards may be used grooved side upwards or the fine ribbed side upwards - depending on your choice. The fine ribbed side has the better slip resistance and has been graded as the top side. You will need to cut the 3m deck boards in half and when laying the deck boards alternate the 4m & 1.5m deck boards.
A. Marking out position of deck
i. Choose a site where the front to the deck will have the lowest step-up.  The site can slope downwards up to 600 mm.  Balustrade should be used on falls of over 300mm.  Mark out the perimeter with pegs and line.  Check for squareness by measuring for equal diagonals.  Clear any obstructions that may interfere with the deck or pergola - ground levelling is not required as the posts will be used to level the deck.
ii. Mark out where the Metal Post Anchors will be positioned, (see plan above) (please read the Pergola assembly instructions first if fitting a pergola over the raised deck- see note no. 4 below)  - when in place they will have their bolts facing to the front or back and their outside edges will be approx 2.0m-2.2m apart - both ways and distances to outside should be equal . Check for squareness of the post anchors by measuring for equal diagonals.
B. Driving Post Anchors into the ground, cutting and fixing Posts
i. Cut a piece of post to use inside the Post Anchors when driving them into the ground. With the Bolts facing the front or back drive the Anchors into the ground continually checking and adjusting for uprightness and squareness.  Place Support Joist upright against the Post Anchors running front to back raised off the ground approx. 30 mm at the front (use a  board laid flat) - level the joist and temporarily support at the back.  Repeat for Support Joist on the other side of the post. Repeat for the other Post Anchors
ii. Cut the post so that there will be short posts each coming in line with the top of the Support Joists from the base of the Post Anchor. Make cuts with a slight fall from front to back. Brush Preserver onto the cut surfaces of the Posts
iii. Fix Posts into Post Anchors  (where possible, ensure cut edge is at the top with the fall from front to back to assist clearing rainwater). Posts may require easing to fit the Post Anchors -Brush Preserver onto the cut surfaces -Check verticals & tighten the bolts on the Post Anchors to ensure good grip. It is advisable to concrete in the Post Anchors after fixing all the joists. 

2. Fixing Support Joists to Posts

A. Select the strongest joists with the fewest and smallest knots for use as the 4 main Support Joists which are attached to the posts.
i. Ensure that the first 2 Support Joists will be fixed to the Post which will be on the highest ground. (i.e. the one where the Support Joist will be nearest the ground and preferably the front entrance to the Deck).  Place the first Support Joist on the outside and second Support Joist  on the inside of the Posts running from front to back - so that there is an equal projection from both Posts.   Position these first 2 Support Joists against first Post approx. 30 mm off the ground at the front
 - Use one of the 80mm screws to locate the joists before drilling and use the Drill Bit provided to make a hole all the way through the joists, the metal socket (if necessary) and the post - drill the hole 40 mm from the bottom of the Support Joist and 10 mm offset from the centre of the post.  Do not drill the second hole into the same post yet because it is necessary to create the levels with all the other Posts and Support Joists first.  Temporarily fix both Joists to the Post with a Bolt.  It may be necessary to remove the first joists and finish off the drilling through the second joists if the drill bit is not quite long enough.  This can happen if the posts and joists are not square.
ii. Checking that the level of the first 2 Support Joists are correct, position them against the back
(and centre where applicable) Post and drill, as (2Ai). You may not be drilling through the metal of the Post Sockets if there is a slope. 
iii
. Using one of the other timbers as a straight edge align & level the next 2 Support Joists with first 2 Support Joists and position against the second front Post matching projections and drilling as (2Ai).   Checking that the levels of these 2nd 2 Support Joists are correct, position them against the 2nd set of posts Post and drill as (2Ai).  Check that the Joists attached to 1st set of Posts are level with those attached to 2nd set of Posts.  Adjust if necessary. Repeat for 3rd set of posts.
B. Drilling a second hole in each post, Fixing the Washers and tightening the Bolts
i. When all Support Joists are level - Drill a second hole 40mm from the top of the Support Joists and 10 mm offset the other way from the centre of each post.  Do this for all Posts.  You may not be drilling through the metal of the Post Sockets for these upper holes - if you have this situation -   Mark the Posts at the top of the Joists. Remove all Bolts and the Support Joists from their temporary fixings.  Keep by the Posts. Position Washers where necessary, in between the Posts and the Support Joists to compensate for the gaps created by the Post Anchors, push all 8 Bolts through the Support Joists, Posts and Post Sockets using a washer against the joist at the back before tightening the nut - ensuring the washers have sunk a little into the joists.

C.
Fixing Post Noggins between Support Joists (this is only for the 3m & 3.6m decks)
i. Cut the post off-cuts into 2 No. approx. 90 mm  cubes and Brush Preserver onto the cut surfaces   Position the post noggins in the centre between and in line with the bottom of the Support Joists.
Post Noggins are used to prevent distortion on the Support Joists and should not be left out of all decks with 3m or 3.6m in positions C, D or E.joist hanger (inverted)

3. Fixing Outer & Centre Joists

A. Hanging Front & Rear Joist from Support Joists
i. Position Front Joist against front of all 6 main support joists and ensure equal projections from both outside Support Joists.   Place 6 Joist Hangers so that they rest on top of  all 6 Support Joists i.e. open end pointing downwards with the back against Front Joist and when correctly aligned - flush with the top of the Support Joists and with equal projections - mark the positions on Front Joist where the 6 screws in each Hanger will be fixed.  Remove and fix the hangers to Front Joist using the Small Screws. To give maximum strength the screws will be a tight fit and may need ‘starting’ with a tap from a hammer. Place Front Joist over Support Joists so that it rests on the Hangers - secure to all Support Joists by screwing into the timber on one side.
corner detail

ii. Repeat for Rear Joist

B. Fixing the Side Joists to Front & Rear Joists and Hanging the Centre Joists
i .Lay the Side Joists on the ground with the inside face pointing upwards.  Position the longer side of the Corner Brackets on the Side Joists so that they are flush with the end and are 20 mm in from the top & bottom.  Use 3 of the Screws to fix each Corner Bracket to the Side Joists.  Ensure that the tops of all Joists are flush and fix the Side Joists, using Small Screws, into each end of the Front & Rear Joists - this can be flush (especially when joining two decks together) or, if a single deck, up to 60mm in from each end to provide an overhang for the deck boards.
joist hanger
ii.
Mark the Front & Rear Joists (see guide above for distances) for the remaining Centre Support Joists.  Position the remaining Hangers at the bottom of the Front & Rear Joists centrally across each of the 2 marks with the open end pointing upwards, so that the Centre Joists will later rest on the Hangers.  Fix the Hangers with the 6 Small Screws onto the Front & Rear Joists.  Drop the Centre Joist into place - and secure by screwing into the timber on one side.

C.
Fixing Noggins between Support Joists (only for C, D or E support joists over 3.6m)
i. Cut the 4" planed timber noggins to fit between all joists in line with the centre posts (marked in green in the drawing above) and Brush Preserver onto the cut surfaces   Position them in line with the bottom of the Support Joists and fix with the 50mm screws screwing at an angle into the support joists.
Noggins are used to prevent distortion on the Support Joists and should not be left out.

D. Before fixing Balustrade and/ or Deck Boards concrete around post sockets. 
Dig out approx. 300 mm deep and 400 mm square around each post socket, recheck they are upright & square with plumb rule or level and fill with concrete to prevent movement

4. If using pergola - click here  N.B. Always fix Pergola Posts, Supports, and Tops before fixing Deck boards

5. If using Balustrade - click here  Please note that the newel posts must be fitted before the deck boards

6. Fixing the Deck Boards please check from the list above as to how many deck boards are used and the expected overhang.

i. Position the first deck board, with the correct overhang, and ensure it is flush at the ends of the front joist.   Screw in 2 decking screws in line with each joists the front one going into the front joist.

ii.
Space out the deck boards so that the front of first deck board is 150mm from the front of the second deck board this maybe 3mm to 7mm depending the moisture content of the deck boards  and ensure flush at the ends with the board in front.  Screw in 2 decking screws approx. 25mm from the front and back in line with each joists.
iii. The back board should overlap the back joists the recommended overhang (see list above).

7. Finishing & Maintenance

i. As all timbers are pressure preserved further treatment is not necessary and the timber will fade to a natural grey colour.  If preferred, the deck may be coated with Decking Stain to the colour of your choice. If there is any build of moss, after winter use a jet sprayer or an anti-fungicidal and hose down to remove.  To restore the colour apply a further coat of Decking Stain.

ii. Dispose of all waste timber in your dustbin - do not burn.  Wash hands after handling timber - especially before eating.  Always wear safety glasses when using power tools.

Help Line -  For more information - contact Peter Dale on 01457 855259  or email diydeals@hotmail.co.uk

deck welcomeground decks with 4" planed joistsground decks with 6" planed joistsRaised DecksPergola Decks BalustradePrices

All rights reserved.  19/08/2010.

You may print this copy for use during erection.  This leaflet may not be reproduced in whole or in part without the prior written approval of Peter Dale.